Class 6 & 7 – SCM (Prof. Suhas Rane)

SRM – Supplier relationship management.

Key characteristic –

· Paying critical vendors on time

· Account manager is single source of contact between vendor and company

Graph

X-Axis (Importance of part - VED from top to bottom); Y-Axis (Expenditure - ABC from left to right)

Routine

Bottleneck

Critical

Leverage

Location in graph

Bottom Left

Top Left

Top Right

Bottom Right

Example

MRO

Type Washer 0 low value, but critical in production

Engines, Fuel injection pump

Music system

Characteristic

Desirable, C-Item

Vital, C-Item

Vital, A-Item

Desirable, A-Item

Standard item

Often non std, but could be either

Often non std, but could be either

Standard

Bulk buy

Small lot purchase

Small lot purchase

Bulk buy

· Routine – Fountain pens; Keep on continuously buying from the vendor directly; rates are fixed once in the beginning of the year. Normally one supplier is there for such MRO items. In case price of the goods increases, company then quotes a range of price.

· Leverage – High priced but bought in bulk. Hence, price is negotiated with many suppliers. Hence, switching cost is low. Here, the purchase manager is in distant relationship as Sales team deals with the suppliers.

· Bottleneck – Relationship with suppliers is most important. This is not attractive for vendors, hence, company should have at least 2 vendors. Vendors are negotiated for volumes. A team player should be the purchase officer.

· Critical – Few items, very high valued hence, very high risk associated. The vendor should be the REAL supply chain partner. Trust is most important. Hence, share Point of Sale, use CPFR, long term commitment.

Freshness Index (Used by Tata) – (FI) = Sales from products (less than a year old) / Total Sales

Postponement – It is a strategy where the finished product is postponed by preparing all / major standard parts first. Reason for the delay is assemble the standard parts in a fashion to prepare a different yet desired output product as demanded by user. Hence, new customized products are made from the standard components and hence, new finished products are available for the customer.