IT Project Management (End Term Exam)
Professor Moradian
Time: 3 Hours (Open Book/Open Notes/ Closed Internet)
Instructions:
All questions are compulsory
Make valid assumptions wherever necessary. State them clearly.
Submit soft copy for question 4
Question 1 – Reference: “Case Study – Scafest”. Carry out risk analysis. What could be the likely events, their drivers and suggested risk mitigation actions, etc.
Question 2 – “Case Study – DU Singer Hospital Products”, prepare WBS
Question 3 – “Case Study – Blue Spider”, prepare a likely Project Charter list.
Question 4 – For a project as indicated below, use MS Projects and suggest a resource leveling plan within the available slack only
There are only 4 numbers of resources PQR & 4 numbers of resources XYZ available
Activity | Duration (wks) | Preceding Activity | Resource Requirement PQR | Resource Requirement XYZ |
A | 2 | - | 2 | 0 |
B | 3 | - | 0 | 3 |
C | 12 | - | 1 | 1 |
D | 6 | A | 3 | 1 |
E | 2 | B | 1 | 2 |
F | 4 | D | 2 | 0 |
G | 3 | E | 0 | 4 |
H | 8 | F,G | 2 | 2 |
I | 4 | C,H | 1 | 1 |